SAT Help 24×7
MathChapter 14: Rational Expressions
Reading progress0%
About 32 minutes
On this page

Work problems become manageable when one whole job is represented by \(1\). A worker's rate is the fraction of the job completed per unit of time, so each contribution is rate times time.

Rate, time, and work

Work relationship
\[\text{work done}=\text{rate}\times\text{time},\qquad r=\frac1t\]

If a worker completes one job in \(t\) hours, the rate is \(1/t\) job per hour.

A standard work-rate table
WorkerTime aloneRateTime workingWork done
A\(6\) h\(1/6\) job/h\(x\) h\(x/6\)
B\(4\) h\(1/4\) job/h\(x\) h\(x/4\)
Together\(1/6+1/4=5/12\)\(x\) h\(5x/12\)
Worked example

Two workers together

A completes a job in \(6\) hours and B in \(4\) hours. How long do they need together?

  1. Write rates

    A's rate is \(1/6\); B's is \(1/4\) job per hour.

  2. Add rates

    \(1/6+1/4=5/12\) job per hour.

  3. Invert the combined rate

    Time for one job is \(1\div(5/12)=12/5\) hours.

\(12/5\) hours, or \(2\) hours \(24\) minutes.

Partial and staged work

A staged-work timelineCompute each stage with rate times time, then use the remaining fraction of one whole job.
  1. \(2\left(\frac16\right)=\frac13\)

    Two hours at one sixth job per hour completes one third.

  2. \(1-\frac13=\frac23\)

    Two thirds of the job remains.

  3. \(\frac16+\frac14=\frac5{12}\)

    Together they complete five twelfths per hour.

  4. \(\frac{2/3}{5/12}=\frac85\)

    The final stage lasts eight fifths of an hour.

Worked example

One worker starts, then another joins

A can finish a job in \(6\) hours. A works alone for \(2\) hours, then B, who can finish alone in \(4\) hours, joins. How much longer is needed?

  1. A completes \(2/6=1/3\); therefore \(2/3\) remains.

  2. Their combined rate is \(1/6+1/4=5/12\).

  3. Remaining time is \((2/3)\div(5/12)=8/5\) hours.

\(8/5\) hours, or \(1\) hour \(36\) minutes after B joins.

Units and context

Keep units aligned

Hours

A rate of \(1/5\) job per hour multiplied by \(3\) hours gives \(3/5\) job.

Minutes

Convert \(90\) minutes to \(3/2\) hours before using an hourly rate.

Multiple jobs

If the target is \(N\) jobs, set total work equal to \(N\), not \(1\).

Model any work problem

  1. Choose one unit

    Convert all times to hours or all to minutes.

  2. Write each rate

    Use jobs divided by time; for one job in \(t\), use \(1/t\).

  3. Separate stages

    Compute work in each interval and add contributions.

  4. Set the target

    Total work equals \(1\) for one whole job unless the problem states otherwise.

  5. Validate

    Check positivity, units, faster-together behavior, and whether the answer matches total or remaining time.

SAT strategy

Common mistakes and traps

  • Adding completion times instead of rates.
  • Using \(t\) instead of \(1/t\) as a rate.
  • Forgetting work already completed in an earlier stage.
  • Mixing minutes and hours.
  • Reporting time after a helper joins when total elapsed time was requested.
  • Accepting a together-time longer than the fastest individual time.
Mini check

Combined-rate check

A and B need \(10\) and \(15\) hours alone. Is \(12\) hours a possible together-time?

Show answer and explanation

Answer: No.

Together they must finish in less than \(10\) hours. In fact, the combined rate is \(1/10+1/15=1/6\), so they need \(6\) hours.

Key takeaways

Key takeaways

  • Represent one whole job by \(1\).
  • Individual rate is the reciprocal of individual time.
  • Add work contributions, not raw times.
  • Separate staged intervals and subtract completed work.
  • Check units and contextual plausibility.
Continue learning

Put these notes into practice

Apply the ideas with SAT-style questions, then reinforce key details with flashcards.